RTG - Navkar CFS Mumbai continues to save nearly 75% of operational costs with our custom solution for electrification of RTG
Client – Navkar CFS Mumbai
Problem Statement
With the rising diesel prices, the RTG crane operations with fossil fuels is untenable. The customer Navkar CFS Mumbai, wanted a cost-effective and viable solution for operating the cranes. The essential aspects here were to create an economical solution that was fast and could manage low height installation.
Solution
Electroflex Engineering understood the client requirement and suggested the retro-fitting of existing RTG crane to electrify it. The electrification of RTG would save operations cost. The next challenge was to ensure the speed of operations and still be economical.
Our technicians created a highly economical solution by finding and replacing nearly 80% of the components with Indian counterparts. This brought down the project cost by a huge margin.
The current installation height is just 2800mm from the ground, another requirement of the client that we fulfilled. The solution continues to be economical and fast.